Locally Preferred Alternative
social-media

Locally Preferred Alternative

Draft Locally Preferred Alternative:
University Corridor

draft-lpa-smClick to view larger map.The draft Locally Preferred Alternative (LPA) was released in September 2013 and is shown in the map to the right. It is a combination of Alternatives 2 and 3; Alternatives 1 and 4 were not recommended for advancement. All four alternatives can be viewed below in "How was the draft LPA identified?"

  • The proposed route runs primarily down University Boulevard from Menaul to Avenida Cesar Chavez, where it would zig east to Yale and south to the Sunport.
  • The route would also take a brief detour to the UNM Main Campus via Lomas, Las Lomas, and Redondo.
  • Most of this route would include Bus Rapid Transit features such as bus-only lanes to bypass traffic congestion and improve travel times. 
  • Several park-and-rides would be incorporated into this system, including the existing UNM remote parking lots that are currently served by UNM shuttles, as well as a new public park-and-ride north of Menaul.

Tell us your thoughts!

Email This email address is being protected from spambots. You need JavaScript enabled to view it..

After the LPA is finalized, it will be further refined through future engineering and planning phases.

Learn more about Bus Rapid Transit >>

See presentation, display boards and past materials >>

Ridership

  • Preliminary projections estimate that over 17,000 people per day would use the system, more than all three Rapid Rides combined and equivalent to 38% of ABQ Ride’s total ridership. 40 percent of the ridership would come from UNM remote parking lots, with the rest coming primarily from UNM and CNM students, staff, and faculty, as well as local residents.
  • Traveling east on Avenida Cesar Chavez would allow buses to serve the UNM South Lot. Any recommended alignment should serve the South Lot, which would generate more ridership than the rest of UNM’s remote lots combined – about 7,000 trips per day. However, if the South Lot could be relocated to University Boulevard near The Pit, the proposed route would follow University all the way to Gibson and then over to Yale, as shown by the dashed lines. This alignment would provide better service to UNM South Campus and more economic development opportunities, particularly with Lobo Development’s planned 50-acre commercial development south of The Pit.

Where would the bus lanes be located?

Bus lanes would be located at the outside of the street in some instances – in which case they would share the lane with right-turning vehicles – and in the median in others. Typical street cross-sections are shown below. To accommodate these bus lanes, University between Avenida Cesar Chavez and Martin Luther King would be reduced from six lanes to four lanes, and Yale between Cesar Chavez and Gibson would be reduced from four lanes to two. These sections currently have excess capacity, and lane reductions are not expected to have much impact on existing traffic. Under this proposal, UNM would also have to limit traffic on Las Lomas and West Redondo to buses and local traffic only, to minimize bus delays.

No lanes would be removed on Avenida Cesar Chavez or University north of Lomas. Instead, bus guideways would be built in the existing medians.

Riders would board the bus at about 14 stations along the route, an average of one every half-mile. Where the buses operate in the median, the stations would also be located in the median, and riders would access them using signalized crosswalks.

Street cross-sections:

typicals-v3-01-sm

typicals-v3-02-sm

typicals-v3-03-sm

typicals-v3-04-sm

typicals-v3-05-sm

typicals-v3-06-sm

station-curbsideConceptual curbside station

station-medianConceptual median station

How was the draft LPA identified?

This study used an Alternatives Analysis (AA) process, which was required for projects seeking federal funding. Building upon the travel needs identified in the 2011 scoping report, the AA began in June 2012 and has relied heavily on public and stakeholder involvement from the beginning. MRCOG assembled a technical team consisting of representatives from the City of Albuquerque, Bernalillo County, UNM, CNM, the Sunport, Rio Metro RTD, and other stakeholders, which has advised the team at every step of the process. Through September 2013, there have been five series of formal public meetings to get input at critical stages of the study, and MRCOG has also conducted surveys and held other events to get feedback.

The AA began with the identification of the area’s transportation needs and the project goals and objectives. By January, stakeholders identified a “long list” of possible transit routes, which was then vetted by the technical committee, public meetings, and preliminary analysis. Low-performing routes such as Girard were removed, leaving a “short list” of possible routes. This short list was again vetted by the technical committee and the public and was subjected to more detailed analysis. The results of this analysis, as well as earlier versions of the routes, are available on our Materials page. From the short list, four specific alternatives were identified, as shown below. Alternative 3 performed the best and was recommended as the Draft Locally Preferred Alternative, followed by Alternative 2 as described earlier. The Draft LPA was presented for public input in September 2013, and once feedback is incorporated, the LPA will be finalized and project development will begin.

Click image caption to view larger map.

alternative-1-sm Alternative 1 alternative-2-smAlternative 2

alternative-3-smAlternative 3 alternative-4-smAlternative 4

How often would buses run?

Buses would operate 16 hours per day Monday through Saturday, and 12 hours per day on Sundays. Within the core service area – roughly between the UNM Cancer Center and the sports stadiums – buses would arrive every five minutes during peak periods, and every 10 minutes off-peak. In the northern and southern ends of the corridor, buses would arrive every 15 minutes during peak periods and every 30 minutes off-peak. In other words, every third bus would leave the core service area and continue north to Menaul or south to the Sunport. During weekends, buses would run every 15 minutes throughout the corridor. Special operating schedules could be developed for sports games and other special events.

Who will operate it?

This service could potentially be operated by ABQ Ride, the Rio Metro Regional Transit District, or another entity such as UNM. The study team is exploring these alternatives to determine the most appropriate operator.

How much will this cost?

It will take an estimated $62 to $65 million to build this Bus Rapid Transit system, including vehicles, a new park-and-ride facility, maintenance facility upgrades, and general system costs. This is a deliberately conservative (high) estimate, including a 40% contingency for unexpected costs, and it is expected that the actual costs will be significantly lower. Up to 80% of the funding could come from the Federal Transit Administration, with the rest provided by local agencies and institutions.

Once built, the system would cost about $3.2 to $3.3 million every year to operate. This cost would be the responsibility of the operating agency and participating institutions such as UNM and CNM.

What are the next steps?

In late September, MRCOG will submit a request to the Federal Transit Administration to enter into Project Development, which will allow us to further flesh out details such as who owns and operates the system, how it is financed, and the roles of each stakeholder group (UNM, CNM, etc.). Project Development will also allow us to create more detailed ridership and cost estimates and begin some of the engineering work. After that, the project can compete for federal funding to build the system. If funding is granted, the project could open to riders as early as fall 2017.

end faq

rendering1-cnm-smallRendering 1 - CNM

rendering2-unm-cancer-center-smallRendering 2 - UNM Cancer Center

rendering3-isotopes-park-smallRendering 3 - Isotopes Park

rendering-4-university-central-smallRendering 4 - University and Central

Home

Transportation

Special Studies

Workforce

Local Food

Land & Water

Economic Development

Region & People

About Us

Calendar

Contact Us

MRCOG OfficeMid-Region Council of Governments
809 Copper Avenue, NW
Albuquerque, NM 87102
Phone: 505-247-1750
Fax: 505-247-1753
Contact us by Email

Directions to MRCOG Offices

Google Translate

English French German Portuguese Spanish

Our Other Sites